diff --git a/src/assets/newImgs/pumpGY/suggestP.png b/src/assets/newImgs/pumpGY/suggestP.png new file mode 100644 index 0000000..cfb21fd --- /dev/null +++ b/src/assets/newImgs/pumpGY/suggestP.png Binary files differ diff --git a/src/assets/newImgs/pumpGY/suggestP.png b/src/assets/newImgs/pumpGY/suggestP.png new file mode 100644 index 0000000..cfb21fd --- /dev/null +++ b/src/assets/newImgs/pumpGY/suggestP.png Binary files differ diff --git a/src/views/sponeScreen/projectHM/projectDX.vue b/src/views/sponeScreen/projectHM/projectDX.vue index 7fb3f83..958ce25 100644 --- a/src/views/sponeScreen/projectHM/projectDX.vue +++ b/src/views/sponeScreen/projectHM/projectDX.vue @@ -3,14 +3,21 @@
2024-08-25 (24小时累计60mm降雨)
-1,该项目设计总调蓄容积35.8m³;
-2,海绵设施留蓄水量2.6m³;
-3,溢流时长1.4h,排出3.2m³
-4,根据进出口的ss对比,海绵设施的净化能力达标
+2024-08-26 降雨起止时间1:15-3:45,24小时累计降雨量20.4mm,降雨等级 中雨
+1,项目设计最大控制容积 3796.52m³
+2,项目设计标准达标情况(降雨量≤54.62mm时,径流总量控制率≥90%):本场降雨径流总量控制率92%,达标
+3,雨水管网产流开始时间1:45,结束时间4:45,累计流量843.5m³,最大水深0.5m